    常规环氧地坪漆施工工序:1、地面打磨清理干净,无尘打磨机打磨;2、涂刷高效环氧地坪漆底漆,根据不同的地面做不同的环氧地坪漆底漆,地面情况不同,环氧地坪漆底漆耗漆量也不一样,新地面环氧地坪漆耗漆量通常是0.15kg/㎡左右,起砂严重的地面环氧地坪漆耗量则可达 0.5kg/㎡以上;3、环氧地坪漆底漆固化之后,涂刷无溶剂环氧环氧地坪漆中涂,根据地面环氧环氧地坪漆涂刷道数,每平米环氧地坪漆耗漆量 0.3kg/㎡;

    Conventional construction procedures of epoxy floor paint: 1. Clean up the ground and polish with dust-free grinder; 2. Paint high-efficiency epoxy floor paint primer, make different epoxy floor paint primers according to different ground conditions, the amount of epoxy floor paint primer consumption is different, the amount of new ground epoxy floor paint consumption is usually 0.1. The consumption of epoxy flooring paint with serious sand rising can reach 0.5kg/or above at 5kg/. 3. After curing, epoxy flooring paint is coated with solvent-free epoxy flooring paint. According to the number of brushing paths of epoxy flooring paint, the consumption of epoxy flooring paint is 0.3kg/per square meter. 

    4、涂刷环氧腻子,用于填补细缝,环氧地坪漆耗漆量 0.2kg/㎡;

    4. Apply epoxy putty to fill the seam. The paint consumption of epoxy floor paint is 0.2kg/. 

    5、刮涂两遍环氧地坪漆面漆,环氧地坪漆耗漆量 0.3kg/㎡,自流平面漆是先刮涂一道环氧地坪漆,然后再镘涂一道环氧地坪漆,耗漆量为 1.1kg/㎡;

    5. Scrape two times of epoxy floor paint, the consumption of epoxy floor paint is 0.3 kg/. Self-flow floor paint is to scrape an epoxy floor paint first, then apply an epoxy floor paint, the consumption of paint is 1.1 kg/. 

    6、为了更好的防止环氧地坪磨损漆膜破损,可以在涂刷环氧地坪漆面漆后,固化之后再涂刷一道清漆环氧地坪漆自流平,这样更好的防止环氧地坪漆漆膜长久摩擦破损,有效的延长了地坪的使用寿命。

    6. In order to prevent the wear and tear of epoxy flooring paint film, one can apply a varnish epoxy flooring paint to self-leveling after painting the epoxy flooring paint, which can better prevent the long-term friction and tear of the epoxy flooring paint film and effectively prolong the service life of the flooring. 


    环氧地坪铺装设基本流程

    Basic process of epoxy floor paving 

    (0) 面涂批补:采用面涂材料配石英细粉批涂,填补中涂较大颗粒间的空隙,待完全固化后,用无尘打磨机打磨地面,用吸 尘器吸尽灰尘、打磨平整。

    (0) Surface painting batch repairing: using surface coating material with quartz powder batch coating, filling the gap between larger particles in the middle coating, to be fully solidified, using dust-free grinder to grind the ground, using a vacuum cleaner to absorb dust, grinding flat. 

    (1) 基层处理:打磨掉松散层、脱层及水泥残渣,使之坚硬、平整,并增加地坪涂层与地面的附着力。

    (1) Base treatment: grinding loose layer, delamination and cement residue to make it hard and smooth, and increase the adhesion between the floor coating and the ground. 

    (2) 底涂施工:把环氧封闭底漆配好后,辊涂、刮涂或刷涂,使其充分润湿混凝土,并渗入到混凝土内层。

    (2) Primer construction: After the epoxy sealing primer is matched, roll, scrape or brush are applied to wet the concrete fully and infiltrate into the inner layer of the concrete. 

    (3) 中涂施工:将中涂材料与适量的石英砂充分混合搅拌均匀,用镘刀镘涂成一定厚度的平整密实层。

    (3) Intermediate coating construction: mix the middle coating material with appropriate amount of quartz sand and mix evenly, and coat it with trowel to form a uniform and compact layer with a certain thickness. 

    (4) 面涂批补:采用面涂材料配石英细粉批涂,填补中涂较大颗粒间的空隙,待完全固化后,用无尘打磨机打磨地面,用吸 尘器吸尽灰尘、打磨平整。

    (4) Surface painting batch repairing: using surface coating material with quartz powder batch coating, filling the gap between the larger particles in the middle coating, to be fully solidified, using dust-free grinder to grind the ground, using a vacuum cleaner to absorb dust, grinding flat. 

    (5) 面涂施工:将环氧色漆及固化剂混合均匀后,可镘涂、刷涂、辊涂或喷涂,使其流平,获得平整均匀的表面涂层。

    (5) Surface coating construction: After mixing epoxy paint and curing agent evenly, it can be sprayed, brushed, rolled or sprayed to make it level and obtain a smooth and uniform surface coating. 


    工厂车间环氧地坪漆施工步骤:

    Plant floor epoxy floor paint construction steps: 

    1、基面清理:用机动打磨机磨粗基面的同时,再用手动打磨机清除需要彻底清理的基面;

    1. Base surface cleaning: While grinding rough basement surface with a motor grinder, then using a manual grinder to remove the basement that needs to be thoroughly cleaned; 

    2、清洁、检查基底:对基面吸尘干净后,检查基底有无裂缝、空壳,如有,则须深层切割清理后用环氧树脂砂浆填补,由于环氧树脂不容水,所以在处理过程中只能进行干处理,清理时不可野蛮敲打,以免敲松边上的基层。

    2. Clean and check the base: After cleaning the base surface, check whether there are cracks and empty shells in the base. If so, it must be cut deep and filled with epoxy resin mortar. Because the epoxy resin is not water-tolerant, it can only be dry treated in the process of cleaning, so it can not be brutally knocked when cleaning, so as to avoid loosening the base on the edge. 

    3、环氧树脂底漆涂装:在进行基底处理的同时,可进行环氧底涂 涂装,施工配料时要注意施工进度与用料的平衡,不可一次开料过多,保证材料在涂装时仍符合可使用时间,在胶化前被涂刷完,让材料保持良好的渗透性,保证粘接性能;

    3. Epoxy resin primer coating: epoxy primer coating can be carried out at the same time as the base treatment. The balance between construction progress and materials should be paid attention to during construction proportioning, so as to ensure that the material still meets the usable time in painting and is painted before gelatinization, so as to maintain good permeability of the material, and ensure that the material can not be overloaded at one time. Adhesive property; 

    4、在底涂固化后,首先用环氧树脂中涂配石英砂镘刮环氧石英砂浆N遍,以增加整个漆膜的厚度加强漆膜的抗压、抗冲击等物理性能;

    4. After solidification of the primer, the epoxy resin is first coated with quartz sand to scrape the epoxy quartz mortar N times, so as to increase the thickness of the whole film and enhance the physical properties of the film, such as compression and impact resistance. 

    5、环氧树脂批土中涂:砂浆层固化后,再刮环氧批土2道,封闭砂眼和气孔,打磨腻子并吸尘干净。

    5. Epoxy resin batch soil coating: after curing the mortar layer, scrape the epoxy batch soil 2 ways, seal sand holes and stomata, Polish putty and dust clean. 

    6、环氧树脂面涂涂装:打磨中涂层,在确保基面被完全封闭的情况下,按设计要求施工环氧树脂平涂面涂2道,施工时将面涂材料搅拌均匀后滚涂施工;涂装施工的环境要求:施工基面应保持干净、干燥,无其他工程施工交叉作业,室内空气相对湿度宜小于85%,当湿度过大时应停止施工;

    6. Epoxy resin surface coating: coating in polishing, in order to ensure that the base surface is completely closed, two epoxy resin flat coatings should be constructed according to the design requirements, and the surface coating materials should be stirred evenly before rolling coating construction; the environmental requirements of coating construction: the construction base surface should be kept clean and dry, and there is no cross-work of other engineering construction. Industry, indoor air relative humidity should be less than 85%, when humidity is too large, we should stop construction. 

    7、现场清理维护、地坪养护:面涂完成后将有关施工材料、工具搬离现场,严密封闭保护完成饰面,至少48小时后才可允许人进入行走。并不可带进泥沙,漆膜完全固化一般需7天时间,期间应避免进行其他工程施工、搬运、安装等施工。

    7. On-site cleaning and maintenance, floor maintenance: After finishing the surface painting, the relevant construction materials and tools will be removed from the site, and the finish decoration will be tightly sealed and protected. At least 48 hours later, people can be allowed to walk. No sediment should be brought in. It usually takes 7 days to solidify the paint film completely. During this period, other engineering construction, handling and installation should be avoided. 


    标签:   环氧地坪 地坪 环氧地坪漆 环氧地坪施工