    水性环氧地坪漆施工工艺该如何做

    2018-10-31 07:05:43 无锡盛发地坪科技有限公司 阅读

    其实水性环氧地坪漆在施工方面与普通环氧地坪漆的步骤大部分相同,主要有五部分,分别为底涂、半途、批补、面涂和养护,详细施工情况如下所示:1、底涂:将混凝土基材处理完毕并清理干净后就可进行底涂(辊涂或刷涂),辊涂或刷涂应平均,厚薄一致。该底涂具有一定的透水汽功能,能增强基材强度并增加涂层对基材的附着力。

    In fact, water-borne epoxy floor paint in the construction of most of the same steps as ordinary epoxy floor paint, there are five main parts, respectively, primer, half way, batch, surface coating and maintenance, the detailed construction as follows: 1, primer: concrete substrate treatment and clean up after the primer (roll or brush) Roll coating or brush should be uniform and thick. The primer has a certain water vapor permeability function, can enhance the strength of the substrate and increase the adhesion of the coating to the substrate. 2、中涂:在已配好的水性环氧地坪漆(中涂)中加入石英砂和石英粉配成水性环氧砂浆环氧地坪漆,用镘刀将其平均涂布,用于增加厚度及涂层抗压强度。

    2. Intermediate coating: Waterborne epoxy mortar floor paint was prepared by adding quartz sand and quartz powder into the prepared waterborne epoxy floor paint (Intermediate coating). It was evenly coated with trowel knife to increase the thickness and compressive strength of the coating.

    3、批补:中涂后用砂纸打磨环氧地坪,并用水性环氧地坪漆(中涂)与石英粉配成的腻子依实际需要施工数道,要求达到平整无孔洞,无批刀印和砂磨印为准。4、面涂:用辊涂将水性环氧地坪漆面涂辊涂两道,完工后要求整体地面光泽柔和、洁净、颜色均一、无空鼓。

    3. Batch repairing: grinding the floor with sandpaper after intermediate coating, and using water-borne epoxy floor paint (intermediate coating) and quartz powder to compounded putty according to the actual needs of several construction, requirements to achieve flat without holes, no batch knife printing and sand grinding. 4. Topcoat: Two rolls of water-borne epoxy floor paint are applied with roll coating. After completion, the whole floor is required to be smooth, clean, uniform in color and no empty drum.

    5、养护:面层实干需要24H,在这期间应进行封锁,比免影响表面洁净光滑的效果。3D后方可上人,完工保养7天后方可正式投入使用(25℃为准,低温时需适度延长)

    5. Maintenance: It takes 24H for the surface to be dry. During this period, it should be blocked so as not to affect the effect of surface cleanliness and smoothness. It can be put into use after 7 days of maintenance (25 C, moderately prolonged at low temperature)