    环氧地坪涂装前检查哪些基本项目

    2018-10-22 07:38:44 无锡盛发地坪科技有限公司 阅读

    环氧地板漆涂装前对面材质量进行检查,以便根据地面状况设计合理的涂装方案和重点采取一些质量控制措施。 一般检查有哪些基本项目?几天环氧地坪漆厂家安广为大家讲解下:1、地面平整度:用2米直尺检查,记录间隙值,对地面过高处进行标记,以便重点打磨,对过低处采用砂浆修补。

    Before the epoxy floor paint is painted, the quality of the face material is checked, so as to design a reasonable painting scheme and take some quality control measures according to the ground condition. What are the basic items of general inspection? A few days floor paint factory Anguang for everybody to explain: 1, ground smoothness: with 2 meters ruler check, record the gap value, mark the ground too high, in order to focus on grinding, the use of mortar repair too low.

    2、基材含水量检查:应向客户了解混凝土已养护多久了,底层有没有施工防水层,在养护期间的天气状况等。一般来说,夏季晴天通风良好时的楼上15天养护期限就可以了,冬季,雨季养护期应长些。一般需约1个月。在施工前采用混凝土含水率测量仪对基材含水率进行测量是必要的,对测量点采用如下原则选择:A、底层(一楼);B、靠近门窗或外墙处;C、局部在混凝土浇铸完工后沾过水的地点;D、落水管、排水沟等附近。如没有测量仪,采用薄膜覆盖法也很有效,要点是薄膜一定不能漏气并要贴地密封严密。

    2. Inspection of moisture content of base material: We should know how long the concrete has been cured, whether there is a waterproof layer in the bottom layer, weather conditions during the curing period, etc. Generally speaking, the maintenance period of 15 days upstairs on a fine summer day with good ventilation is OK. In winter, the maintenance period of rainy season should be longer. It usually takes about 1 months. Before construction, it is necessary to measure the moisture content of the base material by using the concrete moisture content measuring instrument. The following principles should be adopted to select the measuring points: A, the bottom floor (first floor); B, near doors, windows or external walls; C, part of the place where the concrete has been dipped after casting; D, water pipes, drains, etc. If there is no measuring instrument, the film covering method is also effective, the main point is that the film must not leak and must be tightly sealed.

    3、混凝土强度检查:主要检查混凝土表面是否有起砂现象,局部是否的空鼓现象,地面何处有钢筋类物质(机械打磨时如不注意易损坏机器),然后一一标注并记录。对强度特差的混凝土,处理时应特别注意,这种地面打磨作用不大,而涂装前彻底吸尘倒很重要,吸尘后再用无溶剂底榉(稀释下更佳,有利于增加渗透力)打底,使之尽量深入渗透,反应固化后锚固混凝土。

    3. Concrete strength inspection: mainly check whether there is sand on the surface of the concrete, whether there is local empty phenomenon, where the ground reinforcement material (mechanical grinding if not pay attention to easy damage to the machine), and then one by one marked and recorded. Special attention should be paid to the special strength of concrete when dealing with the ground grinding effect is not small, and before painting, it is very important to thoroughly dust down, after vacuum, solvent-free beech (dilution is better, conducive to increasing permeability) to make it as deep as possible penetration, reaction solidification after anchoring concrete.

    4、其它方面的检查:因环氧地板漆施工需要洁净封闭的涂装环境,任何一个细节的疏忽都可能造成返工或缺陷,造成损失,因而在进场施工前需检查以下方面:A、门窗是否已完好,屋面、水管等是否有漏水隐患;B、照明、电力等设施是否齐备,如需自备,应计划好;C、拟施工期间的天气状况。

    4. Other aspects of inspection: because the epoxy floor paint construction needs a clean and closed painting environment, any details of the negligence may cause rework or defects, resulting in losses, so before the construction site to check the following aspects: A, doors and windows are intact, roof, water pipes, etc. whether there is a hidden danger of leakage; B, lighting, electricity If the facilities are available, if necessary, plan well; C, weather conditions during construction.