    不容错过的金刚砂地坪施工工艺及注意事项

    2018-10-20 08:27:01 无锡盛发地坪科技有限公司 阅读

    金刚砂环氧地坪,俗称耐磨硬化环氧地坪,大多用于对地面要求高强度的耐磨性的工业区域,包括工厂、码头、重载机械厂、停车场、车间、物流仓库、商业卖场等。金刚砂地坪的耐磨性是因为其材料中包含骨料、波兰特种水泥及颜料和外剂等经过合理配制生产,通过专业的施工工艺让耐磨材料与混凝土地面相结合,因此才能做到拥有坚固耐磨的特性。接下来就让皇家地坪小编来告诉你金刚砂地坪的施工工艺及注意事项吧!

    Diamond floors, commonly known as wear-resistant hardened floors, are mostly used in industrial areas requiring high-strength wear resistance to the ground, including factories, docks, heavy-duty machinery factories, parking lots, workshops, logistics warehouses, commercial stores and so on. The abrasion resistance of diamond floor is due to its material including aggregates, Polish special cement, pigments and additives through the rational preparation of production, through professional construction technology so that wear-resistant materials and concrete floor combination, so as to achieve a strong wear-resistant characteristics. Next let the Royal floor Bian Xiaobian to tell you the construction technology and precautions of diamond floor. 

    一、施工工艺流程

    1. Construction process flow 

    1、首先混凝土基面找平层要求厚度30mm-50mm以上,强度为C25以上,现场塌落度75-100mm,砼表面应密实、平整、且无泌水。

    1. Firstly, the thickness of the leveling layer on the concrete foundation should be more than 30mm-50mm, the strength should be more than C25, the site collapse should be 75-100mm, and the concrete surface should be compact, flat and no bleeding. 

    2、然后混凝土初凝时使用指压测试,留下3-5mm印迹,可开始施工。

    2, and then use the finger pressure test when the concrete is initially solidified, leaving the 3-5mm imprint, which can start construction. 

    3、其次手工撒播地面硬化料,待其吸收混凝土水分变湿即可使用抹光机压实、收光。

    3. Secondly, hand-sown hardened ground materials, when it absorbs moisture from concrete can be used to compact and light. 

    4、接着用手工抹刀收光机械施工的区域。

    4, then use manual spatula to receive light machinery construction area. 

    5、然后表面完成后即用特殊养护剂,用细雾状喷射施工养护,切记不要用塑料布覆盖。

    5. Then the surface is finished with special curing agent, spraying construction and maintenance with fine mist, remember not to cover with plastic cloth. 

    6、最后进行切割伸缩缝和使用密封涂料。

    6. Finally, cut the expansion joint and use the sealing coating. 

    工地上的金刚砂地坪

    Diamond floor at construction site 

    工地上施工未完成的金刚砂地坪

    Unfinished emery floor at construction site 

    二、注意事项

    Two, matters needing attention 

    1、选择有施工经验人员进行专门的水平控制和面层施工以保证质量。

    1, select construction experience personnel to carry out special level control and surface construction to ensure quality. 

    2、做好现场协调、组织管理,最好提前制定合理的交底工作,以充足人力、物力确保连续浇筑及与面层施工速度的配合,保证施工按计划进行。

    2. To do a good job of site coordination, organization and management, it is better to work out reasonable bottoming work in advance, in order to ensure the continuous pouring and surface construction speed with sufficient manpower and material resources, to ensure that the construction proceeds according to plan. 

    3、严把材料进场关,根据要求选择恰当的面层材料。

    3, strictly introduce materials into the field and select appropriate surface materials according to the requirements. 

    4、最好进行混凝土凝结时间试验,选择适宜的混凝土配合比及水泥外加剂;尽量缩短混凝土的运输时间,及时卸料;合理安排浇筑顺序,不随意留置施工缝;混凝土凝结过快使金刚砂面层无法施工,混凝土凝结过慢金刚砂施工时大量水泥浆向上挤冒而影响表面质量。

    4. It is better to carry out concrete setting time test, select appropriate concrete mix proportion and cement admixture; shorten the concrete transportation time as far as possible, unload materials in time; arrange the pouring sequence reasonably, do not leave construction joints at will; the rapid setting of concrete makes the surface layer of diamond sand unable to be constructed, and the slow setting of concrete in the construction of diamond sand. When a large number of cement paste upwards, the surface quality will be affected. 

    5、在浇筑前,气温高时需用水冲洗模板降温,浇筑时保证振捣密实,严格控制振捣时间,移动距离和插入深度,严防漏振及过振。

    5. Before pouring, when the temperature is high, water should be used to flush the formwork to cool down. When pouring, compact vibration should be ensured. The time of vibration should be strictly controlled. The moving distance and insertion depth should be strictly controlled to prevent leakage and over-vibration. 

    6、加强成品保护意识,特别是彩色金刚砂地坪的成品保护。

    6, enhance the awareness of finished products protection, especially the protection of finished products of color emery floor. 