    热风炉检修前需要做哪些准备工作

    2018-12-02 11:41:37 无锡盛发地坪科技有限公司 阅读

    1.确定热风炉检修类别:根据热风炉历年的运行和修理资料,设备安全状况,设备缺陷,机械磨损记录,结合本企业的生产情况,确定热风炉检修类别,作出热风炉计划修理的安排。2.作好技术准备:按照热风炉检修类别的标准项目和在这次检修中需要改进的设备和项目,根据质量标准的技术要求,作好图纸资料,工艺施工的技术准备工作。同时提出原料、备件、工具计划、作好物质准备。

    1. Determine the type of hot-blast stove maintenance: According to the operation and repair data of hot-blast stove over the years, equipment safety status, equipment defects, mechanical wear records, combined with the production situation of the enterprise, determine the type of hot-blast stove maintenance, make the arrangement of hot-blast stove planned repair. 2. Make technical preparation: According to the standard items of hot blast stove maintenance category and the equipment and projects that need to be improved in this maintenance, and according to the technical requirements of quality standards, make technical preparation for drawing materials and process construction. At the same time, the plan of raw materials, spare parts, tools and material preparation are put forward.

    3.停炉检查:按计划把热风炉停下来,对热风炉进行内外部的详细检验,校对热风炉图纸是否与其实际情况相符,评价设备的技术状况,修改和补充标准项目的内容,并据以进一步修改和充分材料、备件、工具。

    3. Stop checking: Stop the hot stove according to plan, check the inside and outside of the hot stove in detail, check whether the drawing of the hot stove conforms to the actual situation, evaluate the technical status of the equipment, modify and supplement the contents of the standard items, and further modify and adequately modify the materials, spare parts and tools accordingly.

    4.确定各种修理定额:如确定大,中,小修的劳动量定额和设备修理的停歇时间定额,作好经济预算等。

    4. Determine various repair quotas: for example, determine the labor quota for large, medium and small repairs and the stop time quota for equipment repairs, and make a good economic budget, etc.

    5.安排施工:制定安全措施,编制进度表,指定专人负责,组织施工力量,配备现场技术指导和质量检验。在施工过程中,严格按质量标准执行自检、互查、专职检验的“三检制”,对各项工作进行考核,开展全面质量管理,提高检修质量。

    5. Arrangement of construction: formulation of safety measures, preparation of schedule, appointment of special personnel responsible for, organization of construction force, equipped with on-site technical guidance and quality inspection. In the process of construction, the "three inspection systems" of self-inspection, mutual inspection and full-time inspection are strictly carried out according to the quality standards. The work is assessed, the total quality management is carried out, and the quality of maintenance is improved. 